Case PW-1048
7 Railway Cottages, Enfield
Rear and side-return extension
What this means
A dissent has been received. That does not necessarily stop the project, but it may require surveyor appointments and an Award. The platform will not choose a surveyor for either owner.
Next action. Explain the agreed-surveyor and separate-surveyor options. Do not appoint anyone automatically.
- Postcode
- EN1 4PQ
- Complexity
- medium
- Professional
- Unassigned — matching in progressNot yet introduced · independent firm · insurance not verified
- Opened
- 20 Aug 2026
- Two neighbours
- Combined notices may be required
Notice
- Type
- Party structure and adjacent excavation (combined draft)
- Status
- served
- Version
- 3
- Served
- 1 Sept 2026
- Method
- Personal service by the case manager, witnessed note on file
- Proof
- POS-1048-B
- Response by
- 15 Sept 2026
- Response
- dissent
Response dates use a 14-day general rule and still need a professional to confirm them against the notice that was actually served.
Professional reviewDocuments
- Nothing on the file yet.
Payment
Notice service — two owners. Surveyor fees not yet quoted.
£468.00
Net £390.00 · VAT £78.00 · paid
Marked paid in this preview. No money moved.
Messages
Case desk · portal · 2026-09-16 09:05 UTC
Marta Klein has dissented in writing. That is a normal statutory step. You can discuss an agreed surveyor if both of you are willing. If not, each owner may appoint their own surveyor. We have not appointed anyone.
Parties
Building owner
Daniel Okoye
7 Railway Cottages, EN1 4PQ
Adjoining owner
Marta Klein
9 Railway Cottages, EN1 4PQ
Adjoining owner
Freeholder — unnamed